Road Work Updates

Special Notices


We will try to keep this site up to date and accurate as possible. Changes to the schedules may occur without notice. Please try to avoid these areas during construction or plan on delays when navigating through the work zones. Paving dates are subject to change due to weather conditions.

Current Construction Schedule

 Roadway  Activities and Duration
Armanella Street Final paving completed. Project scheduled to end soon thereafter.
Baskin Drive Final paving completed. Project scheduled to end soon thereafter.
Burnett Road Final pavement has been installed.  Line striping is scheduled for Monday, April 26th.  Project to be completed soon thereafter.
Fuller Road

This project has begun with completion date of August 2023.  Utility work is currently underway.  Traffic delays should be expected throughout the duration of this project.  Lane manipulation with traffic barrels / cones will be ongoing this year for utility work along Fuller Road, Sheridan Street and the Veteran’s Memorial Bridge.

New Lombard Road

Road will be closed to through traffic during work hours beginning on April 19th. Local traffic only will be allowed during these hours.  Through traffic will be allowed after weekday work hours and on the weekends.  Project completion is scheduled by June 1st.

Massachusetts Turnpike (I90)  The MassDOT will begin a project in May 2021 to realign the entrance and exit ramps at (former) Exit 6 and involves work along Burnett Road / I291 and the ramp to Fuller Road.  (This is a MassDOT project.)


Installation of driveway aprons and sidewalks scheduled for the week of 5/23/16
Installation of water main scheduled for 7/27- 8/5/16
Installation of water main scheduled for 7/27- 8/5/16
Reclamation and grading of roadway 8/2- 8/12
Reclamation and grading of roadway 8/2- 8/12
Reclaim/remove asphalt 9/6- 9/8
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Grading of roadway 9/4- 9/14

Grading of roadway 9/4- 9/14
Fine grading 3/4- 3/5
Installation of dense grade gravel 3/8
Paving 3/9
Adjustment of structures 4/8- 4/11
Reclaim of roadway 4/12- 4/15
Driveways, sidewalks 6/3- 6/14
Paving 6/4- 6/5
Driveways, sidewalks 6/10- 6/21
Paving 6/10- 6/11
Driveways, sidewalks 6/24- 7/12
No construction week of 7/1
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th