Road Work Updates

Special Notices

We will try to keep this site up to date and accurate as possible. Changes to the schedules may occur without notice. Please try to avoid these areas during construction or plan on delays when navigating through the work zones. Paving dates are subject to change due to weather conditions.


Current Construction Schedule

 Roadway Activities and Duration
Columba Street Full depth reconstruction of Columba Street from Laurel Street to Ward Street. Water main replacement has been completed, as well as the final pavement overlay. Punch list items and line striping are expected to be wrapped up by the end of the year.

Safety Improvements
Project

This project includes improvements to the existing crosswalks along the northerly section of Chicopee St (north of the "Y", the northerly Chicopee St/Meadow St intersection). These locations include Charbonneau Terrace / Bolduc Lane, Leslie Street and Whitman Street. The improvements at each of these locations include a new median/refuge island, accessible ramps with detectable warning panels, new signage, continental crosswalk striping (longitudinal bars), and RRFBs (Rapid Rectangular Flashing Beacons - pedestrian actuated).

Existing crosswalks on Chicopee Street at Sarah Jane Park and Florence Street will be upgraded with RRFBs and continental crosswalk striping.  Additional existing crosswalks along Chicopee Street and Meadow Street will be upgraded with continental crosswalk striping and in some locations, new signage.

A new crosswalk on Broadway north of Thornwood St includes accessible ramps with detectable warning strips, new signage, continental crosswalk striping, and RRFBs.   New crosswalks on Broadway at Pine Street / Alvord Avenue and East Street near 39 East Street are also included in the project.
 
A new traffic island at the corner of Cherryvale Ln and New Ludlow Rd has been constructed.

The work at the locations north of "The Y" on Chicopee Street is scheduled to start the week of August 7th.

.


Installation of driveway aprons and sidewalks scheduled for the week of 5/23/16
Installation of water main scheduled for 7/27- 8/5/16
Installation of water main scheduled for 7/27- 8/5/16
Reclamation and grading of roadway 8/2- 8/12
Reclamation and grading of roadway 8/2- 8/12
Reclaim/remove asphalt 9/6- 9/8
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Grading of roadway 9/4- 9/14

Grading of roadway 9/4- 9/14
Fine grading 3/4- 3/5
Installation of dense grade gravel 3/8
Paving 3/9
Adjustment of structures 4/8- 4/11
Reclaim of roadway 4/12- 4/15
Driveways, sidewalks 6/3- 6/14
Paving 6/4- 6/5
Driveways, sidewalks 6/10- 6/21
Paving 6/10- 6/11
Driveways, sidewalks 6/24- 7/12
No construction week of 7/1
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th