Road Work Updates

Special Notices


We will try to keep this site up to date and accurate as possible. Changes to the schedules may occur without notice. Please try to avoid these areas during construction or plan on delays when navigating through the work zones. Paving dates are subject to change due to weather conditions.

Current Construction Schedule

 Roadway  Activities and Duration
Columba Street  Full depth reconstruction of Columba Street from Laurel Street to Ward Street. Water main replacement has been completed and binder course pavement has been installed as of 9/6/22. Curb work is scheduled to begin in the coming weeks. 
Fuller Road

Night paving will begin on Fuller Road starting Thursday, May 26, 2022.  The current schedule for the initial paving is as follows:


Thursday 5/26 – 7pm to 5am

Tuesday 5/31 – 7pm to 5am

Wednesday 6/1 – 7pm to 5am

Thursday 6/2 – 7pm to 5am

This work will be starting at Memorial Drive, progressing easterly towards Old Fuller Road; including the Sheridan Street intersection.  The first two courses (base and intermediate courses) of pavement will be installed to approximately the bottom of the hill east of the Moose Lodge.  Please seek alternate routes, if possible.


The Fuller Road project is a full reconstruction of the road, which is being run by the MassDOT.  The reconstruction means that the entire cross-section of the road is being re-done; providing a new road base and three courses of new pavement.


The past year (2021) had been predominantly dedicated to moving and improving utilities along the road corridor to make way for the widening and repaving of Fuller Road.  Gas mains and utility poles have been relocated.  New drainage for the road has been mostly installed.  New water main along the entire length of Fuller Road was also installed under this contract.  The installation of these items is why there are currently many trench patches along the road.


The schedule for the Fuller Road project has a completion date of August 2023, but much of the improvement of the road surface will occur this calendar year (2022).  We appreciate the public’s patience while this large project is constructed.  Please seek alternate routes, if possible.

 Road Resurfacing Granby Road resurfacing, Grattan Street to Baystate Road, final paving is scheduled for Monday 9/12/22. Granby Road, Davitt Memorial Bridge to Grattan Street, is scheduled for final paving on Tuesday 9/13/22. All scheduled paving is weather permitting.
Massachusetts Turnpike (I90) The MassDOT will begin a project in May 2021 to realign the entrance and exit ramps at (former) Exit 6 and involves work along Burnett Road / I291 and the ramp to Fuller Road.  (This is a MassDOT project.)


Installation of driveway aprons and sidewalks scheduled for the week of 5/23/16
Installation of water main scheduled for 7/27- 8/5/16
Installation of water main scheduled for 7/27- 8/5/16
Reclamation and grading of roadway 8/2- 8/12
Reclamation and grading of roadway 8/2- 8/12
Reclaim/remove asphalt 9/6- 9/8
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Grading of roadway 9/4- 9/14

Grading of roadway 9/4- 9/14
Fine grading 3/4- 3/5
Installation of dense grade gravel 3/8
Paving 3/9
Adjustment of structures 4/8- 4/11
Reclaim of roadway 4/12- 4/15
Driveways, sidewalks 6/3- 6/14
Paving 6/4- 6/5
Driveways, sidewalks 6/10- 6/21
Paving 6/10- 6/11
Driveways, sidewalks 6/24- 7/12
No construction week of 7/1
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th