Road Work Updates

Special Notices


We will try to keep this site up to date and accurate as possible. Changes to the schedules may occur without notice. Please try to avoid these areas during construction or plan on delays when navigating through the work zones. Paving dates are subject to change due to weather conditions.

Current Construction Schedule

 Roadway  Activities and Duration
Asinof Avenue Paving scheduled for Monday June 28th
Dale Street Paving scheduled for Tuesday June 29th
Hampden St Paving scheduled for Monday June 28th
Munger Rd Awaiting paving schedule from paving contractor


Installation of driveway aprons and sidewalks scheduled for the week of 5/23/16
Installation of water main scheduled for 7/27- 8/5/16
Installation of water main scheduled for 7/27- 8/5/16
Reclamation and grading of roadway 8/2- 8/12
Reclamation and grading of roadway 8/2- 8/12
Reclaim/remove asphalt 9/6- 9/8
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Grading of roadway 9/4- 9/14

Grading of roadway 9/4- 9/14
Fine grading 3/4- 3/5
Installation of dense grade gravel 3/8
Paving 3/9
Adjustment of structures 4/8- 4/11
Reclaim of roadway 4/12- 4/15
Driveways, sidewalks 6/3- 6/14
Paving 6/4- 6/5
Driveways, sidewalks 6/10- 6/21
Paving 6/10- 6/11
Driveways, sidewalks 6/24- 7/12
No construction week of 7/1
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th